Shandong Fortune Chemical Co., Ltd. was established on November 22, 2006 with a registered capital of 20 million yuan. It is a wholly-owned subsidiary of Shandong Huayang Deer Chemical Co., Ltd. and is located in Ningyang Chemical Industrial Park (formerly Ningyang County Biochemical Base), covering an area of 100 mu. The company plans to invest 2.6 million yuan to build 30000 tons/year hexahydrate magnesium nitrate project in the existing plant area, mainly using the original 30000 tons/year calcium ammonium nitrate and 20000 tons/year calcium nitrate project workshop and part of the equipment, and new part of the equipment. After the completion of the project, the annual output of 60000 tons of six water magnesium nitrate.
Shandong Fortune Chemical Co., Ltd. 60000 tons/year hexahydrate magnesium nitrate project
Public participation in environmental impact assessment for the first time
Name and Summary of 1. Construction Project
Project Name: 60000 Tons/Year Magnesium Nitrate Hexahydrate Project
Construction unit: Shandong Fortune Chemical Co., Ltd.
Shandong Fortune Chemical Co., Ltd. was established on November 22, 2006 with a registered capital of 20 million yuan. It is a wholly-owned subsidiary of Shandong Huayang Deer Chemical Co., Ltd. and is located in Ningyang Chemical Industrial Park (formerly Ningyang County Biochemical Base), covering an area of 100 mu. The company plans to invest 2.6 million yuan to build 30000 tons/year hexahydrate magnesium nitrate project in the existing plant area, mainly using the original 30000 tons/year calcium ammonium nitrate and 20000 tons/year calcium nitrate project workshop and part of the equipment, and new part of the equipment. After the completion of the project, the annual output of 60000 tons of six water magnesium nitrate. There is no new labor capacity for the project, and the production adopts a three-shift working system, with each shift working 8 hours and 300 days per year.
Name and contact information of 2. construction unit
Construction unit: Shandong Fortune Chemical Co., Ltd.
Contact address: Ningyang Chemical Industry Park (formerly Ningyang County Biochemical Industry Base)
Contact: Zhu Lisheng
Contact number: 15169817658
E-mail: 15169817658@163.com
3. name and contact information of the environmental impact assessment agency undertaking the assessment work
Evaluation Unit: Shandong Rudi Environmental Technology Co., Ltd.
Contact: Wang Gong
Contact number: 18953801660
E-mail: china_eia_report@163.com
Web Links to 4. Public Comments Form
http://www.mee.gov.cn/xxgk2018/xxgk/xxgk01/201810/t20181024_665329.html
Working Procedures and Main Work Contents of 5. Environmental Impact Assessment
The working procedures include:(1) preparation stage: study the relevant documents, carry out the investigation of the current environmental situation, screen the key evaluation projects, and determine the evaluation work level. (2) Formal work stage: further engineering analysis and status investigation and monitoring, and environmental impact prediction and evaluation. (3) Preparation of the report stage: summarize information and data, put forward environmental protection measures and suggestions, give conclusions, and complete the preparation of the report.
The main work contents include (1) engineering analysis: introduce the general situation of the project, the environmental situation of the project construction site and the environmental protection objectives, analyze the impact on the environment and its evaluation at different stages in the process of project implementation, and put forward suggestions and measures for environmental protection. (2) Conformity analysis with relevant planning: analyze the opinions of governments at all levels, planning and environmental protection departments where the project is located. (3) Current situation of environmental quality: monitor and evaluate the current situation of environmental quality in the construction area in accordance with the requirements of national laws and regulations. (4) Environmental impact prediction: predict the main environmental factors of the construction project and evaluate the prediction results. (5) Ecological protection measures: put forward reasonable and feasible measures and countermeasures to control pollution and protect the ecological environment, so as to control and reduce or reduce the negative impact caused by the construction of the project to the maximum extent. (6) Public participation: public participation shall be conducted by means of public participation such as environmental information announcement and public opinion survey, and the feedback of public participation shall be reflected in the EIA, and the conclusion of adoption or non-adoption shall be given. (7) Put forward the conclusion of environmental impact assessment: put forward the conclusion of environmental impact assessment on the basis of the above work.
Main matters 6. soliciting public opinions
Whether the Project will aggravate the pollution to the local environment;
③The attitude of taking mitigation measures for the project; ④The effect of the construction of the project on the local economic development;
⑤ Whether the project is supported or not; ⑥ Other opinions or suggestions on environmental protection of the project.
Main ways of 7. public input
(1) Within ten days from the date of the announcement, the construction unit or the entrusted environmental impact report preparation unit shall provide the public with the inquiry and inspection services of relevant materials.
(2) If the public has environmental protection opinions on the construction project, they can express their opinions to the construction unit or the environmental impact report preparation unit by telephone, letter or E-Mail within ten days from the date of this announcement, or they can express their opinions. Form a written text and send it to the local environmental protection authority.
Annex 1: Public Participation in Environmental Impact Assessment of 30000 Tons of Annual Magnesium Nitrate Hexahydrate Project of Shandong Fortune Chemical Co., Ltd. First Publicity
Annex 2: Statistics on Environmental Information Disclosure of Key Pollutants in Ningyang County in 2019
Share to
Subsidiaries:http://www.cfhg-chem.cn/
Address: No.06 Ge Shi Road, Ning Yang Economic Development Zone, Taian City, Shandong Province
Corporate Email:hydier@dier-chem.com
TEL:
Mobile Swipe
Public Number QR Code